Thursday, July 31, 2008

We have established this blog to provide updates on the progress of the Foggy Morning Glen development.

We have encountered many weather delays as it rained all winter and spring! Our contractor said "this is the most rain I've seen in 14 years". The construction of Foggy Morning Glen is nearing completion and the entrance gate was recently finished. The utilities are all in and the installation of the sewer system has begun. After completion of the sewer, the asphalt will be poured, the clearing and seeding along the roadways will be done, and Foggy Morning Glen will be ready for some homes.

We are very excited about the development and we, ourselves, will begin building our own home on Lot #9 in the Spring. We are in the process of finalizing our choice of house plans and look forward to moving into our new home by Fall of 2009.

Lot #13/14 has also been sold and the owners plan to build their home sometime next year.